How do you pre-insulate pipe?

November 2, 2010

At Piping Technology & Products, the term pre-insulated used in the context of pipe supports, refers to the feature of pipe shoes which allows a segment of the insulation to be incorporated into the support. This means that the insulation will be installed into position at the time of the support installation and remain in tact throughout the duration of the pipe support's lifespan.

Pre-Insulated Cryogenic Pipe Support
Pre-Insulated Cryogenic Pipe Support

Why use pipe shoes on un-insulated lines?

You can utilize pipe shoes on un-insulated lines simply to support the pipe or transfer the pipe load to other support components.

Permali Cold Shoes For Carbon Steel Pipe
Permali Cold Shoes for Carbon Steel Pipe

Cryogenic Pipe Supports with Micarta® G-10 for an LNG Facility in Australia

April 16, 2018

Cryogenic Pipe Supports With Micarta® G-10 For An Lng Facility In Australia

Type: Cryogenic Pipe Supports
Size: Pipe Size of 1” to 36”
Material: LTCS Material Tops, Stainless Steel, & Micarta® G-10 Insulation
Design: -50°F
Testing: PMI

Piping Technology and Products supplied these cryogenic and axial stop cold shoes for an LNG facility in Australia. The cryogenic pipe supports were fabricated with LTCS material tops, stainless steel and Micarta® G-10 insulation blocks. They were a wide range of lengths from pipe size of 1” to 36”. The cryogenic temperatures are low as -50°F. A special paint system was used for the carbon steel components to resist rust. PMI testing was performed on the stainless parts prior to the 4-6 week shipping.